Winvic were contracted by Aero Fabrications to construct a new metal aeronautical parts fabrication facility, extending their existing manufacturing operation at Common Lane, Watnall.
At a glance
- Project value: £6m
- Client: Aero Fabrications
- Architect: Williams Architects
- Engineer: Collier Associates
- Programme: 30 weeks
- Completion: December 2019
The works comprised of:
- 71,000 sq ft warehouse
- 4,200 sq ft production and design offices
- Bespoke architectural features around aeronautical theme
- 7m haunch height
- 86,000 sq ft external yard
- Hardstanding
- Service yard
- Car parking
- Soft landscaping works
The works also included a new entrance and visitor reception, administration offices, staff facilities, delivery and despatch points, materials and finished parts stores, fabrication and assembly areas, and paint shop.
Sustainability
- 15% roof lights
- EPC A rated
-
£6 million project value
-
71,000 sq ft aeronautical parts fabrication facility
-
30 week programme
Share this project: