Winvic was appointed by Barwood Developments to design and construct three high spec offices to be built in succession with owner occupier fit out to building four.
At a glance
- Project value: £4.7m
- Client: Barwood Developments Ltd
- Architect: PRC Group
- Engineer: Waldeck Engineers
- Programme: 48 weeks
- Completion: June 2012
- BREEAM: Very Good
Buildings 2 and 3 achieved a BREEAM Excellent rating, with building 4 achieving BREEAM Very Good.
The site had various constraints including a high water course table and limited area for workability of the site. As a result, water management and site co-ordination formed an important factor in the delivery of the project.
-
3 high spec offices
-
48 Weeks
-
BREEAM Excellent rating on units 2 and 3
Works carried out included:
- Demolition of existing buildings following asbestos survey
- Drainage
- Retaining piling to form basement
- De-watering solution to form basement
- External car parking
- Hard and soft landscaping
- Infrastructure works