After the successful completion of the base build, Winvic were contracted to fit-out Euro Car Parts’ 778,000 sq ft distribution warehouse, one of the largest in the Midlands, together with the associated 47,477 sq ft office accommodation and 233,470 sq ft mezzanine at Birch Coppice Business Park.
At a glance
- Project value: £13m
- Client: Euro Car Parts/ KAM
- Architect: UMC Architects
- Engineer: MJM
- Programme: 30 weeks
- Completion: June 2016
Office works include:
- CAT B fit-out
- 6 free standing pod office / welfare facilities
- Ground floor canteen
- Kitchen fit-out
- Walls, ceilings & joinery
- Plumbing
- Warehouse ventilation system
- AC & gas suppression
Other fit-out works include:
- Hi-level & in-rack sprinklers
- Electrical installation including lighting, power, security, data cabling, wi-fi and fire alarm systems throughout
- Specialist Equipment Installation managed on behalf of the client
- Material Handling Equipment comprising of VNA and WA racking, miniload (automated storage and retrieval
system), Stingray shuttle system, picktower, conveyors and associated equipment - Plant equipment comprising of VNA, reach, counter balance and PTT trucks including charging
- Access Control including muster points and turnstiles
- Goods lifts
- Fuel island and refueling station
Watch the internal drone footage here.