At a glance
- Client: Jaynic
- End-user: The Range
- Architect: Frank Shaw Associates
- Engineer: Richard Jackson
- Programme: 39 weeks
- Completion: November 2023
- BREEAM: Excellent
Located at the Gateway 14 business, innovation, and logistics park near junction 50 of the A14 at Stowmarket, Winvic commenced work in December 2022 and handed over the distribution warehouse to client Jaynic and end user The Range for fit out in November 2023.
A total of 3,730 tonnes of steel was used in creating the frame, which was erected extremely quickly for its size in just 9 weeks with up to five mobile cranes in operation at a time. In addition to the warehouse space there is a 21,300 sq ft three storey main office, two 5,100 sq ft two storey transport offices and a 8,800 sq m recycling refuse unit. We installed all the associated drainage, services, on-site road infrastructure and landscaping.
Sustainable features
-
1.2m sq ft industrial unit
-
Low Carbon in Construction
-
BREEAM Excellent
Partners in Communities
During the project, Winvic engaged local partners and the community to tailor social value to meet local needs. Prior to work starting, an Employment & Skills Plan was agreed with the local authority to create opportunities for local people to gain employment and training on the project.