Following the successful completion of the first phase of Mountpark Logistics’ industrial / logistics development at Wide Lane, Southampton, Winvic Construction was appointed to deliver the second phase comprising the construction of 4 high specification BREEAM Excellent distribution warehouses totalling 341,000 sq ft.
At a glance
- Project value: £18.7m
- Client: Mountpark Logistics
- Architect: Michael Sparks Associates
- Engineer: Complete Design Partnership
- Programme: 34 weeks
- Completion: Oct 2018
- BREEAM: Excellent
- Unit 4 – 95,000 sq ft
- Unit 5 – 74,000 sq ft
- Unit 6 – 69,000 sq ft
- Unit 7 – 107,000 sq ft
All units comprise of a single story warehouse together with two storey offices. Externally all works as shown including access road, general hardstandings, car-parking, landscaping, mains services and drainage.
-
£18.7 Million Project Value
-
34 Weeks
-
BREEAM Excellent